Commitments and Contingencies | COMMITMENTS AND CONTINGENCIES We are the subject of, or a party to, a number of pending or threatened legal actions, contingencies and commitments involving a variety of matters, including laws and regulations relating to the environment. Some of these matters are discussed below. For matters for which we have not recorded a liability, we are unable to estimate a range of possible loss because the issues involved have not been fully developed through pleadings, discovery or court proceedings. However, the ultimate resolution of some of these contingencies could, individually or in the aggregate, be material. Environmental Matters We are subject to federal, state, local and foreign laws and regulations relating to the environment. These laws generally provide for control of pollutants released into the environment and require responsible parties to undertake remediation of hazardous waste disposal sites and certain other locations including presently or formerly owned or operated retail marketing sites. Penalties may be imposed for noncompliance. At June 30, 2022 and December 31, 2021, accrued liabilities for remediation totaled $396 million and $401 million, respectively. It is not presently possible to estimate the ultimate amount of all remediation costs that might be incurred or the penalties, if any, that may be imposed. Receivables for recoverable costs from certain states, under programs to assist companies in clean-up efforts related to underground storage tanks at presently or formerly owned or operated retail marketing sites, were $5 million and $6 million at June 30, 2022 and December 31, 2021, respectively. Governmental and other entities in various states have filed climate-related lawsuits against numerous energy companies, including MPC. The lawsuits allege damages as a result of climate change and the plaintiffs are seeking unspecified damages and abatement under various tort theories. We are currently subject to such proceedings in federal or state courts in California, Delaware, Maryland, Hawaii, Rhode Island and South Carolina. Similar lawsuits may be filed in other jurisdictions. At this early stage, the ultimate outcome of these matters remains uncertain, and neither the likelihood of an unfavorable outcome nor the ultimate liability, if any, can be determined. We are involved in a number of environmental enforcement matters arising in the ordinary course of business. While the outcome and impact on us cannot be predicted with certainty, management believes the resolution of these environmental matters will not, individually or collectively, have a material adverse effect on our consolidated results of operations, financial position or cash flows. Other Legal Proceedings In July 2020, Tesoro High Plains Pipeline Company, LLC (“THPP”), a subsidiary of MPLX, received a Notification of Trespass Determination from the Bureau of Indian Affairs (“BIA”) relating to a portion of the Tesoro High Plains Pipeline that crosses the Fort Berthold Reservation in North Dakota. The notification demanded the immediate cessation of pipeline operations and assessed trespass damages of approximately $187 million. On appeal, the Assistant Secretary - Indian Affairs vacated the BIA’s trespass order and remanded to the Regional Director for the BIA Great Plains Region to issue a new decision based on specified criteria. On December 15, 2020, the Regional Director of the BIA issued a new trespass notice to THPP, finding that THPP was in trespass and assessing trespass damages of approximately $4 million (including interest), which has been paid. The order also required that THPP immediately cease and desist use of the portion of the pipeline that crosses the property at issue. THPP has complied with the Regional Director’s December 15, 2020 notice. In March 2021, THPP received a copy of an order purporting to vacate all orders related to THPP’s alleged trespass issued by the BIA between July 2, 2020 and January 14, 2021. The order directs the Regional Director of the BIA to reconsider the issue of THPP’s alleged trespass and issue a new order, if necessary, after all interested parties have had an opportunity to be heard. On April 23, 2021, THPP filed a lawsuit in the District of North Dakota against the United States of America, the U.S. Department of the Interior and the BIA (together, the “U.S. Government Parties”) challenging the March order purporting to vacate all previous orders related to THPP’s alleged trespass. On February 8, 2022, the U.S. Government Parties filed their answer to THPP’s suit, asserting counterclaims for trespass and ejectment. The U.S. Government parties claim THPP is in continued trespass with respect to the pipeline and seek disgorgement of pipeline profits from June 1, 2013 to present, removal of the pipeline and remediation. We intend to vigorously defend ourselves against these counterclaims. We continue to work towards a settlement of this matter with holders of the property rights at issue. We are also a party to a number of other lawsuits and other proceedings arising in the ordinary course of business. While the ultimate outcome and impact to us cannot be predicted with certainty, we believe that the resolution of these other lawsuits and proceedings will not, individually or collectively, have a material adverse effect on our consolidated financial position, results of operations or cash flows. Guarantees We have provided certain guarantees, direct and indirect, of the indebtedness of other companies. Under the terms of most of these guarantee arrangements, we would be required to perform should the guaranteed party fail to fulfill its obligations under the specified arrangements. In addition to these financial guarantees, we also have various performance guarantees related to specific agreements. Guarantees related to indebtedness of equity method investees LOOP and LOCAP MPC and MPLX hold interests in an offshore oil port, LOOP, and MPLX holds an interest in a crude oil pipeline system, LOCAP. Both LOOP and LOCAP have secured various project financings with throughput and deficiency agreements. Under the agreements, MPC, as a shipper, is required to advance funds if the investees are unable to service their debt. Any such advances are considered prepayments of future transportation charges. The duration of the agreements varies but tends to follow the terms of the underlying debt, which extend through 2037. Our maximum potential undiscounted payments under these agreements for the debt principal totaled $171 million as of June 30, 2022. Dakota Access Pipeline MPLX holds a 9.19 percent indirect interest in a joint venture (“Dakota Access”) that owns and operates the Dakota Access Pipeline and Energy Transfer Crude Oil Pipeline projects, collectively referred to as the Bakken Pipeline system or DAPL. In 2020, the U.S. District Court for the District of Columbia (the “D.D.C.”) ordered the U.S. Army Corps of Engineers (“Army Corps”), which granted permits and an easement for the Bakken Pipeline system, to prepare an environmental impact statement (“EIS”) relating to an easement under Lake Oahe in North Dakota. The D.D.C. later vacated the easement. Completion of the EIS may now be delayed as the Army Corps engages with the Standing Rock Sioux Tribe on the tribe’s reasons for withdrawing as a cooperating agency with respect to preparation of the EIS. In May 2021, the D.D.C. denied a renewed request for an injunction to shut down the pipeline while the EIS is being prepared. In June 2021, the D.D.C. issued an order dismissing without prejudice the tribes’ claims against the Dakota Access Pipeline. The litigation could be reopened or new litigation challenging the EIS, once completed, could be filed. The pipeline remains operational. MPLX has entered into a Contingent Equity Contribution Agreement whereby it, along with the other joint venture owners in the Bakken Pipeline system, has agreed to make equity contributions to the joint venture upon certain events occurring to allow the entities that own and operate the Bakken Pipeline system to satisfy their senior note payment obligations. The senior notes were issued to repay amounts owed by the pipeline companies to fund the cost of construction of the Bakken Pipeline system. If the pipeline were temporarily shut down, MPLX would have to contribute its 9.19 percent pro rata share of funds required to pay interest accruing on the notes and any portion of the principal that matures while the pipeline is shutdown. MPLX also expects to contribute its 9.19 percent pro rata share of any costs to remediate any deficiencies to reinstate the permit and/or return the pipeline into operation. If the vacatur of the easement permit results in a permanent shutdown of the pipeline, MPLX would have to contribute its 9.19 percent pro rata share of the cost to redeem the bonds (including the 1% redemption premium required pursuant to the indenture governing the notes) and any accrued and unpaid interest. As of June 30, 2022, our maximum potential undiscounted payments under the Contingent Equity Contribution Agreement were approximately $170 million. Crowley Ocean Partners LLC and Crowley Blue Water Partners LLC In connection with our 50 percent indirect interest in Crowley Ocean Partners LLC, we have agreed to conditionally guarantee our portion of the obligations of the joint venture and its subsidiaries under a senior secured term loan used to finance the acquisition of four product tankers. MPC’s liability under the guarantee for each vessel is conditioned upon the occurrence of certain events, including if we cease to maintain an investment grade credit rating or the charter for the relevant product tanker ceases to be in effect and is not replaced by a charter with an investment grade company on certain defined commercial terms. During the first quarter of 2022, the guarantee for the debt associated with one of the four vessels became effective upon the expiration of the charter for the relevant vessel. As of June 30, 2022, our maximum potential undiscounted payments under this agreement for debt principal totaled $103 million. In connection with our 50 percent indirect interest in Crowley Blue Water Partners LLC, we have agreed to provide a conditional guarantee of up to 50 percent of its outstanding debt balance in the event there is no charter agreement in place with an investment grade customer for the entity’s three vessels as well as other financial support in certain circumstances. As of June 30, 2022, our maximum potential undiscounted payments under this arrangement was $104 million. Other guarantees We have entered into other guarantees with maximum potential undiscounted payments totaling $98 million as of June 30, 2022, which primarily consist of a commitment to contribute cash to an equity method investee for certain catastrophic events, in lieu of procuring insurance coverage, a commitment to fund a share of the bonds issued by a government entity for construction of public utilities in the event that other industrial users of the facility default on their utility payments and leases of assets containing general lease indemnities and guaranteed residual values. Contractual Commitments and Contingencies |