This Amendment No. 1 (“First Amendment”) to the Satellite Program Contract dated March 7, 2018 (the “SPC”) is entered into this 20th day of February 2019 and is made by and between LeoStella LLC, a Delaware limited liability company (“Contractor”) with offices at 12501 East Marginal Way South, South Building, Tukwila, Washington 98168 and BlackSky Global LLC, a Delaware limited liability company (“Purchaser”) with offices at 1505 Westlake Avenue North, Suite 600, Seattle, Washington 98109. Contractor and Purchaser are referred to herein individually as a “Party” and collectively as the “Parties”. Any capitalized terms in this First Amendment that are left undefined shall have that meaning ascribed to them in the SPC.
Recitals
Whereas, Purchaser has requested a new Satellite Delivery Schedule;
Whereas, Contractor has considered the Purchaser’s request for a new Satellite Delivery Schedule; and
Whereas, the Parties wish to memorialize their agreement with respect to a new Satellite Delivery Schedule in this First Amendment and to update certain provisions within the SPC.
Now, therefore, the Parties hereto, in consideration of the mutual promises and covenants herein expressed, agree as follows:
1.0 Article 4(A) and 4(B) of the SPC are amended as follows:
(A) Purchaser shall pay to Contractor for the Work to be performed the Total Price as set forth in in the table below and in accordance with the payment plan and the other provisions of this Contract, as such Total Price may be adjusted in accordance with the provisions of this Contract. The Total Price shall be deemed to include all applicable transportation between Contractor’s facilities and insurance charges up to transfer of risk of loss.
The Total Price shall be:
| | | | | | | | |
Item | | Description | | | [***] Price in USD (per Spacecraft) | |
1-20 | | | Block-2 Spacecraft | | | $ | 3,950,000 | |
| | | | | | | | |
Total Price | | | $ | 79,000,000 | |
| | | | | | | | |
(B) Purchaser shall supply the Scout-04 Payload [***] and End Item Data Package, for integration into the satellite production. The Scout-04 payload shall be delivered by 01 March 2019 and shall meet all requirements of [***] The cost for the Payload shall be the cost of the [***] The [***] The cost for the Purchaser Furnished Scout-04 Payload is [***] borne by the Purchaser for the [***] The [***]