Revenue strategy: The Project is intended to be operated alongside an offtake structure to be negotiated with multiple prospective offtake parties and potentially the sale of Australian Carbon Credit Units or other related financial products.
Timeframe: Project Financial Close is targeted for July 2025, noting there are several key workstreams on the critical path that determine this timeframe. The construction and commissioning period is expected to take approximately 24 months, with the Project designed to operate for 30 years following commissioning.
The parties acknowledge that the Project has two stages:
Stage 1 – Pre-FEED and FEED
Includes Milestones 1 to 2.
During Stage 1 the Recipient will undertake a pre-FEED study and FEED study. The purpose of the studies are to determine the commercial viability of the Project, if the Project remains aligned with the prescribed Outcomes and whether the parties should progress to Stage 2.
Stage 2 – Construction and Operation of the Project
Includes Milestones 3 to 8.
During Stage 2 the Recipient will finance, develop, construct and operate the Project in line with the activities detailed in the Milestones. A 24-month monitoring process will be undertaken with the provision of intermittent operational reports in accordance with the Milestone Deliverables and Knowledge Sharing Deliverables.
The Project involves several Project partners, including:
| | |
Organisation | Role | Description of role in the Project |
Vast Renewables Limited (Vast) | Equity Partner (Project Participant) | Vast is an Australian technology company that with ARENA’s support has developed the world’s leading CSP technology and will be an equity participant in the SM1 Project. |
Vast Solar 1 Pty. Ltd (VS1) | Principal Energy Supplier (Project Participant) | VS1 will deploy Vast’s innovative CSP 3.0 technology, providing both renewable electricity and heat to the Project. |
Mabanaft GmbH & Co. KG (Mabanaft) | Equity Partner and Offtake Partner (Project Participant) | Mabanaft is an equity partner in the Project as well as the proposed offtake partner for the methanol. It is a leading independent and integrated energy company providing its customers with innovative energy solutions for their transportation, heating, industrial and agricultural needs. Mabanaft is active in the import, distribution and marketing of petroleum products, natural gas liquids, chemicals and biofuels, and supports its customers’ transition to cleaner fuels by providing alternative long-term solutions. Mabanaft is interested in the prospect of the proposed project which innovatively intends to utilise the ability to supply 24x7 electricity and heat through Vast's CSP technology to produce low-cost green methanol at scale. |
Fichtner GmbH & Co. KG and Fichtner Australia | Engineering Integrator (Project Participant) | Fichtner will provide the project management and engineering services for the overall project, including the integration of the different packages and the Balance of Plant package. Fichtner |