Commitments and Contingencies | (18) Commitments and Contingencies Qualifying Facilities Liability Our QF liability primarily consists of unrecoverable costs associated with three contracts covered under the PURPA. These contracts require us to purchase minimum amounts of energy at prices ranging from $64 to $136 per MWH through 2029. As of December 31, 2021, our estimated gross contractual obligation related to these contracts was approximately $466.9 million through 2029. A portion of the costs incurred to purchase this energy is recoverable through rates, totaling approximately $388.4 million through 2029. As contractual obligations are settled, the related purchases and sales are recorded within Fuel, purchased power and direct transmission expense and Electric revenues in our Consolidated Statements of Income. The present value of the remaining liability is recorded in Other noncurrent liabilities in our Consolidated Balance Sheets. The following summarizes the change in the liability (in thousands): December 31, 2021 2020 Beginning QF liability $ 81,379 $ 92,937 Settlements (1) (22,497) (18,665) Interest expense 6,061 7,107 Ending QF liability $ 64,943 $ 81,379 ___________________ (1) The settlements amount includes (i) a higher periodic adjustment of $4.3 million due to actual price escalation, which was more than previously modeled; (ii) lower costs of approximately $1.7 million, due to a $2.6 million reduction in costs for the adjustment to actual output and pricing for the current contract year as compared with a $0.9 million reduction in costs in the prior period; and (iii) a favorable adjustment of approximately $7.0 million decreasing the QF liability associated with a one-time clarification in contract term. The following summarizes the estimated gross contractual obligation less amounts recoverable through rates (in thousands): Gross Recoverable Net 2022 $ 80,355 $ 60,639 $ 19,716 2023 82,452 61,280 21,172 2024 75,113 60,706 14,407 2025 60,360 52,950 7,410 2026 55,393 46,274 9,119 Thereafter 113,199 106,563 6,636 Total (1) $ 466,872 $ 388,412 $ 78,460 _____________________ (1) This net unrecoverable amount represents the undiscounted difference between the total gross obligations and recoverable amounts. The ending QF liability in the table above represents the present value of this net unrecoverable amount. Long Term Supply and Capacity Purchase Obligations We have entered into various commitments, largely purchased power, electric transmission, coal and natural gas supply and natural gas transportation contracts. These commitments range from one to 24 years. Costs incurred under these contracts are included in Fuel, purchased power and direct transmission expense in the Consolidated Statements of Income and were approximately $286.7 million, $206.6 million and $222.5 million for the years ended December 31, 2021, 2020, and 2019, respectively. As of December 31, 2021, our commitments under these contracts were $283.2 million in 2022, $269.7 million in 2023, $221.8 million in 2024, $219.4 million in 2025, $172.2 million in 2026, and $1.5 billion thereafter. These commitments are not reflected in our Consolidated Financial Statements. Hydroelectric License Commitments With the 2014 purchase of hydroelectric generating facilities and associated assets located in Montana, we assumed two Memoranda of Understanding (MOUs) existing with state, federal and private entities. The MOUs are periodically updated and renewed and require us to implement plans to mitigate the impact of the projects on fish, wildlife and their habitats, and to increase recreational opportunities. The MOUs were created to maximize collaboration between the parties and enhance the possibility to receive matching funds from relevant federal agencies. Under these MOUs, we have a remaining commitment to spend approximately $26.7 million between 2022 and 2040. These commitments are not reflected in our Consolidated Financial Statements. ENVIRONMENTAL LIABILITIES AND REGULATION Environmental Matters The operation of electric generating, transmission and distribution facilities, and gas gathering, storage, transportation and distribution facilities, along with the development (involving site selection, environmental assessments, and permitting) and construction of these assets, are subject to extensive federal, state, and local environmental and land use laws and regulations. Our activities involve compliance with diverse laws and regulations that address emissions and impacts to the environment, including air and water, protection of natural resources, avian and wildlife. We monitor federal, state, and local environmental initiatives to determine potential impacts on our financial results. As new laws or regulations are implemented, our policy is to assess their applicability and implement the necessary modifications to our facilities or their operation to maintain ongoing compliance. Our environmental exposure includes a number of components, including remediation expenses related to the cleanup of current or former properties, and costs to comply with changing environmental regulations related to our operations. At present, our environmental reserve, which relates primarily to the remediation of former manufactured gas plant sites owned by us or for which we are responsible, is estimated to range between $24.1 million to $30.7 million. As of December 31, 2021, we had a reserve of approximately $26.9 million, which has not been discounted. Environmental costs are recorded when it is probable we are liable for the remediation and we can reasonably estimate the liability. We use a combination of site investigations and monitoring to formulate an estimate of environmental remediation costs for specific sites. Our monitoring procedures and development of actual remediation plans depend not only on site specific information but also on coordination with the different environmental regulatory agencies in our respective jurisdictions; therefore, while remediation exposure exists, it may be many years before costs are incurred. Over time, as costs become determinable, we may seek authorization to recover such costs in rates or seek insurance reimbursement as available and applicable; therefore, although we cannot guarantee regulatory recovery, we do not expect these costs to have a material effect on our consolidated financial position or results of operations. The following summarizes the change in our environmental liability (in thousands): December 31, 2021 2020 2019 Liability at January 1, $ 28,895 $ 30,276 $ 29,741 Deductions (2,799) (2,977) (2,232) Charged to costs and expense 770 1,596 2,767 Liability at December 31, $ 26,866 $ 28,895 $ 30,276 Over time, as costs become determinable, we may seek authorization to recover such costs in rates or seek insurance reimbursement as available and applicable; therefore, although we cannot guarantee regulatory recovery, we do not expect these costs to have a material effect on our consolidated financial position or results of operations. Manufactured Gas Plants - Approximately $22.1 million of our environmental reserve accrual is related to the following manufactured gas plants. South Dakota - A formerly operated manufactured gas plant located in Aberdeen, South Dakota, has been identified on the Federal Comprehensive Environmental Response, Compensation, and Liability Information System list as contaminated with coal tar residue. We are currently conducting feasibility studies, implementing remedial actions pursuant to work plans approved by the South Dakota Department of Agriculture and Natural Resources, and conducting ongoing monitoring and operation and maintenance activities. As of December 31, 2021, the reserve for remediation costs at this site was approximately $8.1 million, and we estimate that approximately $3.0 million of this amount will be incurred through 2025. Nebraska - We own sites in North Platte, Kearney, and Grand Island, Nebraska on which former manufactured gas facilities were located. We are currently working independently to fully characterize the nature and extent of potential impacts associated with these Nebraska sites. Our reserve estimate includes assumptions for site assessment and remedial action work. At present, we cannot determine with a reasonable degree of certainty the nature and timing of any risk-based remedial action at our Nebraska locations. Montana - We own or have responsibility for sites in Butte, Missoula, and Helena, Montana on which former manufactured gas plants were located. The Butte and Helena sites, both listed as high priority sites on Montana’s state superfund list, were placed into the Montana Department of Environmental Quality (MDEQ) voluntary remediation program for cleanup due to soil and groundwater impacts. Soil and coal tar were removed at the sites in accordance with the MDEQ requirements. Groundwater monitoring is conducted semiannually at both sites. At this time, we cannot estimate with a reasonable degree of certainty the nature and timing of additional remedial actions and/or investigations, if any, at the Butte site. In August 2016, the MDEQ sent us a Notice of Potential Liability and Request for Remedial Action regarding the Helena site. In October 2019, we submitted a third revised Remedial Investigation Work Plan (RIWP) for the Helena site addressing MDEQ comments. The MDEQ approved the RIWP in March 2020 and we expect work at the Helena site to continue into 2022. MDEQ has indicated it expects to proceed in listing the Missoula site as a Montana superfund site. After researching historical ownership, we have identified another potentially responsible party with whom we have entered into an agreement allocating third-party costs to be incurred in addressing the site. The other party has assumed the lead role at the site and has submitted a voluntary remediation plan for the Missoula site to MDEQ. At this time, we cannot estimate with a reasonable degree of certainty the nature and timing of risk-based remedial action, if any, at the Missoula site. Global Climate Change - National and international actions have been initiated to address global climate change and the contribution of greenhouse gas (GHG) including, most significantly, carbon dioxide (CO2). These actions include legislative proposals, Executive and Environmental Protection Agency (EPA) actions at the federal level, state level activity, investor activism and private party litigation relating to GHG emissions. Coal-fired plants have come under particular scrutiny due to their level of GHG emissions. We have joint ownership interests in four coal-fired electric generating plants, all of which are operated by other companies. We are responsible for our proportionate share of the capital and operating costs while being entitled to our proportionate share of the power generated. While numerous bills have been introduced that address climate change from different perspectives, Congress has not passed any federal climate change legislation regarding GHG emissions from coal fired plants, and we cannot predict the timing or form of any potential legislation. In 2019, the EPA finalized the Affordable Clean Energy Rule (ACE), which repealed the 2015 Clean Power Plan (CPP) in regulating GHG emissions from coal-fired plants. The U.S. Court of Appeals for the District of Columbia Circuit issued an opinion on January 19, 2021, vacating the ACE and remanding it to EPA for further action. The United States Supreme Court agreed to review the case in October 2021 and oral argument regarding the scope of EPA’s authority to regulate GHG emissions is scheduled to take place February 28, 2022, with a decision expected the following summer. It also is widely expected that the Biden Administration will develop an alternative plan for reducing GHG emissions from coal-fired plants, and in a memorandum dated February 12, 2021, EPA stated its belief that the January 19, 2021 opinion left neither the ACE nor the CPP rules in place. We cannot predict whether or how GHG emission regulations will be applied to our plants, including any actions taken by the relevant state authorities. In addition, it is unclear how pending or future litigation relating to GHG matters will impact us. As GHG regulations are implemented, it could result in additional compliance costs impacting our future results of operations and financial position if such costs are not recovered through regulated rates. We will continue working with federal and state regulatory authorities, other utilities, and stakeholders to seek relief from any GHG regulations that, in our view, disproportionately impact customers in our region. Future additional environmental requirements could cause us to incur material costs of compliance, increase our costs of procuring electricity, decrease transmission revenue and impact cost recovery. Technology to efficiently capture, remove and/or sequester such GHG emissions may not be available within a timeframe consistent with the implementation of any such requirements. Physical impacts of climate change also may present potential risks for severe weather, such as droughts, fires, floods, ice storms and tornadoes, in the locations where we operate or have interests. These potential risks may impact costs for electric and natural gas supply and maintenance of generation, distribution, and transmission facilities. Clean Air Act Rules and Associated Emission Control Equipment Expenditures - The EPA has proposed or issued a number of rules under different provisions of the Clean Air Act (CAA) that could require the installation of emission control equipment at the generation plants in which we have joint ownership. Air emissions at our thermal generating plants are managed by the use of emissions and combustion controls and monitoring, and sulfur dioxide allowances. These measures are anticipated to be sufficient to permit the facilities to continue to meet current air emissions compliance requirements. Regional Haze Rules - In January 2017, the EPA published amendments to the requirements under the CAA for state plans for protection of visibility - regional haze rules. Among other things, these amendments revised the process and requirements for the state implementation plans and extended the due date for the next periodic comprehensive regional haze state implementation plan revisions from 2018 to 2021. The states of Montana, North Dakota and South Dakota are expected to develop and submit to EPA, for its approval, their respective State Implementation Plans (SIP) for Regional Haze compliance. While these states, among others, did not meet the EPA’s July 31, 2021 submission deadline, we still expect each state to submit its SIP in 2022. The draft Montana SIP does not require any additional controls at Colstrip Units 3 and 4. The draft North Dakota SIP does not require any additional controls at the Coyote generating facility, however the EPA, following a preliminary review, has asked North Dakota to reassess its determination regarding Coyote. The draft South Dakota SIP does not require any additional controls at the Big Stone generating facility. Until these SIPs are submitted and approved by EPA, the potential remains that installation of additional emissions controls might be required at these facilities. Jointly Owned Plants - We have joint ownership in generation plants located in South Dakota, North Dakota, Iowa, and Montana that are or may become subject to the various regulations discussed above that have been or may be issued or proposed. Other - We continue to manage equipment containing polychlorinated biphenyl (PCB) oil in accordance with the EPA's Toxic Substance Control Act regulations. We will continue to use certain PCB-contaminated equipment for its remaining useful life and will, thereafter, dispose of the equipment according to pertinent regulations that govern the use and disposal of such equipment. We routinely engage the services of a third-party environmental consulting firm to assist in performing a comprehensive evaluation of our environmental reserve. Based upon information available at this time, we believe that the current environmental reserve properly reflects our remediation exposure for the sites currently and previously owned by us. The portion of our environmental reserve applicable to site remediation may be subject to change as a result of the following uncertainties: • We may not know all sites for which we are alleged or will be found to be responsible for remediation; and • Absent performance of certain testing at sites where we have been identified as responsible for remediation, we cannot estimate with a reasonable degree of certainty the total costs of remediation. LEGAL PROCEEDINGS Pacific Northwest Solar Litigation Pacific Northwest Solar, LLC (PNWS) is a solar QF developer seeking to construct small solar facilities in Montana. We began negotiating with PNWS in early 2016 to purchase the output from 21 of its proposed facilities pursuant to our standard QF-1 Tariff, which is applicable to projects no larger than 3 MWs. On June 16, 2016, however, the MPSC suspended the availability of the QF-1 Tariff standard rates for that category of solar projects, which included the projects proposed by PNWS. The MPSC exempted from the suspension any projects for which a QF had both submitted a signed power purchase agreement and had executed an interconnection agreement with us by June 16, 2016. Although we had signed four power purchase agreements with PNWS as of that date, we had not entered into interconnection agreements with PNWS for any of those projects. As a result, none of the PNWS projects in Montana qualified for the exemption. In November 2016, PNWS sued us in state court seeking unspecified damages for breach of contract and a judicial declaration that some or all of the 21 proposed power purchase agreements it had proposed to us were in effect despite the MPSC's Order. We removed the state lawsuit to the United States District Court for the District of Montana (Court). PNWS also requested the MPSC to exempt its projects from the tariff suspension and allow those projects to receive the QF-1 tariff rate that had been in effect prior to the suspension. We joined in PNWS’s request for relief with respect to four of the projects, but the MPSC did not grant any of the relief requested by PNWS or us. In August 2017, we entered into a non-monetary, partial settlement with PNWS in which PNWS amended its original complaint to limit its claims for enforcement and/or damages to only four of the 21 power purchase agreements. As a result, the damages sought by the plaintiff was reduced to approximately $8 million for the alleged breach of the four power purchase agreements. We participated in an unsuccessful mediation on January 24, 2019 and subsequent settlement efforts also have been unsuccessful. On August 31, 2021, the Court ruled that the four agreements are valid and enforceable contracts and that NorthWestern breached the agreements on June 16, 2016 by refusing to go forward with the projects in spite of the MPSC's Orders. On December 15, 2021, after a three-day trial, the jury determined that PNWS had sustained $0.4 million in damages and the judge subsequently entered judgment against us in that amount. We filed a post-trial motion on January 13, 2022 seeking to have the judgement set aside. On February 9, 2022, the judge denied our post-trial motion. We have 30 days from February 9, 2022 to appeal the judgement to the Ninth Circuit Court of Appeals if we decide to do so. The plaintiff did not seek any post-trial relief and the deadline for doing so has passed. State of Montana - Riverbed Rents On April 1, 2016, the State of Montana (State) filed a complaint on remand (the State’s Complaint) with the Montana First Judicial District Court (State District Court), naming us, along with Talen Montana, LLC (Talen) as defendants. The State claimed it owns the riverbeds underlying 10 of our, and formerly Talen’s, hydroelectric facilities (dams, along with reservoirs and tailraces) on the Missouri, Madison and Clark Fork Rivers, and seeks rents for Talen’s and our use and occupancy of such lands. The facilities at issue include the Hebgen, Madison, Hauser, Holter, Black Eagle, Rainbow, Cochrane, Ryan, and Morony facilities on the Missouri and Madison Rivers and the Thompson Falls facility on the Clark Fork River. We acquired these facilities from Talen in November 2014. The litigation has a long prior history. In 2012, the United States Supreme Court issued a decision holding that the Montana Supreme Court erred in not considering a segment-by-segment approach to determine navigability and relying on present day recreational use of the rivers. It also held that what it referred to as the Great Falls Reach “at least from the head of the first waterfall to the foot of the last” was not navigable for title purposes, and thus the State did not own the riverbeds in that segment. The United States Supreme Court remanded the case to the Montana Supreme Court for further proceedings not inconsistent with its opinion. Following the 2012 remand, the case laid dormant for four years until the State’s Complaint was filed with the State District Court. On April 20, 2016, we removed the case from State District Court to the United States District Court for the District of Montana (Federal District Court). The State filed a motion to remand. Following briefing and argument, on October 10, 2017, the Federal District Court entered an order denying the State’s motion. Because the State’s Complaint included a claim that the State owned the riverbeds in the Great Falls Reach, on October 16, 2017, we and Talen renewed our earlier-filed motions seeking to dismiss the portion of the State’s Complaint concerning the Great Falls Reach in light of the United States Supreme Court’s decision. On August 1, 2018, the Federal District Court granted the motions to dismiss the State’s Complaint as it pertains to approximately 8.2 miles of riverbed from “the head of the Black Eagle Falls to the foot of the Great Falls.” In particular, the dismissal pertained to the Black Eagle Dam, Rainbow Dam and reservoir, Cochrane Dam and reservoir, and Ryan Dam and reservoir. While the dismissal of these four facilities may be subject to appeal, that appeal would not likely occur until after judgment in the case. On February 12, 2019, the Federal District Court granted our motion to join the United States as a defendant to the litigation. As a result, on October 31, 2019, the State filed and served an Amended Complaint including the United States as a defendant and removing claims of ownership for the hydroelectric facilities on the Great Falls Reach, except for the Morony and the Black Eagle Developments. We and Talen filed answers to the Amended Complaint on December 13, 2019, and the United States answered on February 5, 2020. A bench trial before the Federal District Court commenced January 4, 2022 and concluded on January 18, 2022. This bench trial addressed the issue of navigability of the segments at issue. The parties must submit amended findings of fact and conclusions of law, along with post-trial briefing, by April 29, 2022. A decision on navigability is expected following such submissions. Damages were bifurcated by agreement and will be tried separately, should the Federal District Court find any segments navigable. We dispute the State’s claims and intend to vigorously defend the lawsuit. At this time, we cannot predict an outcome. If the Federal District Court determines the riverbeds are navigable under the remaining six facilities that were not dismissed and if it calculates damages as the State District Court did in 2008, we estimate the annual rents could be approximately $3.8 million commencing when we acquired the facilities in November 2014. We anticipate that any obligation to pay the State rent for use and occupancy of the riverbeds would be recoverable in rates from customers, although there can be no assurances that the MPSC would approve any such recovery. Colstrip Arbitration and Litigation As part of the settlement of litigation brought by the Sierra Club and the Montana Environmental Information Center against the owners and operator of Colstrip, the owners of Units 1 and 2 agreed to shut down those units no later than July 2022. In January 2020, the owners of Units 1 and 2 closed those two units. We do not have ownership in Units 1 and 2, and decisions regarding those units, including their shut down, were made by their respective owners. The six owners of Units 3 and 4 currently share the operating costs pursuant to the terms of an operating agreement among them, the Ownership and Operation Agreement (O&O Agreement). Costs of common facilities were historically shared among the owners of all four units. With the closure of Units 1 and 2, we have incurred additional operating costs with respect to our interest in Unit 4 and expect to experience a negative impact on our transmission revenue due to reduced amounts of energy transmitted across our transmission lines. We expect to incorporate any reduction in revenue in our next general electric rate filing, resulting in lower revenue credits to certain customers. The remaining depreciable life of our investment in Colstrip Unit 4 is through 2042. Recovery of costs associated with the closure of the facility is subject to MPSC approval. Three of the joint owners of Units 3 and 4 are subject to regulation in Washington and in May 2019, the Washington state legislature enacted a statute mandating Washington electric utilities to “eliminate coal-fired resources from [their] allocation of electricity” on or before December 31, 2025, after which date they may no longer include their share of coal-fired resources in their regulated electric supply portfolio. As a result of the Washington legislation, four of the six joint owners of Units 3 and 4 requested the operator prepare a 2021 budget reflecting closure of Units 3 and 4 by 2025, and alternately a closure of Unit 3 by 2025 and a closure of Unit 4 by 2027. Differing viewpoints on closure dates delayed approval of the 2021 budget, until it was approved on March 22, 2021. Budgeting for 2022 was also delayed, with the same four joint owners demanding substantial budget reductions, but was ultimately approved on January 21, 2022. Such budgeting pressures may result in future budgets that may not be sufficient to maintain the reliability of Units 3 and 4. While we believe closure requires each owner’s consent, there are differences among the owners as to this issue under the O&O Agreement. On March 12, 2021, we initiated an arbitration under the O&O Agreement (the “Arbitration”), which seeks to resolve the primary issue of whether closure of Units 3 and 4 can be accomplished without each joint owner's consent and to clarify the obligations of the joint owners to continue to fund operations until all joint owners agree on closure. The Arbitration has given rise to three lawsuits concerning the number of arbitrators, the venue and the applicable arbitration laws. The four joint owners from the Pacific Northwest assert the Arbitration must be conducted under the O&O Agreement, with one arbitrator, in Spokane County, Washington, and pursuant to the Washington Arbitration Act. The fifth joint owner asserts the Arbitration must be conducted per the terms of Montana Senate Bill 265 (SB 265), which requires the Arbitration be conducted, with three arbitrators, in Montana and pursuant to the Montana Uniform Arbitration Act. The three initiated lawsuits do not make direct financial demands, and instead, are intended to address issues related to process for the Arbitration. Since the Arbitration was initiated, and despite the litigation, we have worked and continue to work with the other joint owners to arrive at an agreed upon process for the Arbitration. Colstrip Coal Dust Litigation On December 14, 2020, a claim was filed against Talen Montana, LLC, the operator of the Colstrip Steam Plant, in the Montana Sixteenth Judicial District Court, Rosebud County, Cause No. CV-20-58. The plaintiffs allege they have suffered adverse effects from coal dust generated during operations associated with the Colstrip Steam Plant. On August 26, 2021, the claim was amended to add in excess of 100 plaintiffs. It also added NorthWestern, as well as the other owners of the Colstrip Steam Plant, and Westmoreland Rosebud Mining LLC, as defendants. Plaintiffs are seeking economic damages, costs and disbursements, punitive damages, attorneys’ fees, and an injunction prohibiting defendants from allowing coal dust to blow onto plaintiffs’ properties. Since this lawsuit is in its early stages, we are unable to predict outcomes or estimate a range of reasonably possible losses. Other Legal Proceedings We are also subject to various other legal proceedings, governmental audits and claims that arise in the ordinary course of business. In the opinion of management, the amount of ultimate liability with respect to these other actions will not materially affect our financial position, results of operations, or cash flows. |